Lynnwood Link Extension Update

Update from Sound Transit

Sound Transit Update Banner

Another 2015 project milestone achieved

On Friday July 10, the Federal Transit Administration issued a formal Record of Decision (ROD) to Sound Transit for the Lynnwood Link Extension. This important milestone completes the environmental review process, prepares the agency to move into the final design phase of the project early next year and takes the project one step closer to anticipated federal grant funding. The decision keeps the project on track to begin construction in 2018 and open in late 2023.

The ROD defines mitigation measures and other requirements for the project. A summary of environmental determinations and findings is included in the document.


Final design

Sound Transit is set to begin the final design phase of the Lynnwood Link Extension in early 2016 to advance designs on the project’s trackway, stations and art installations. In final design, milestones are associated with a general level of “completeness” of design: 30%, 60% and 100% (ready for construction). Around these milestones, Sound Transit will engage the public and project partners on a variety of project aspects, including station appearance and construction detail.

During final design, Sound Transit will prepare the project for construction by:

  • Developing station designs
  • Conducting additional field work
  • Acquiring permits
  • Incorporating art into project plans
  • Procuring right-of-way
  • Refining construction mitigation measures
  • Defining the construction sequence, schedule and methods
  • Continuing the partnerships with local jurisdictions (ex. station area planning)

Schedule overview 2016-2023

Early 2016 – Project begins the final design phase
Mid 2016 – Station design public meetings start
Late 2016/Early 2017 - Impacted properties confirmed, property owners notified
2018 – Construction begins
Late 2023 – Open for service


For more information

For more information about the Lynnwood Link Extension project, please contact Roger Iwata at 206-689-4904 or roger.iwata@soundtransit.org.  

You can also visit the Lynnwood Link Extension web page.

To report urgent construction matters: please call Sound Transit’s 24-hour construction hotline at 1-888-298-2395.  24-hour construction hotline: 888-298-2395

Sound Transit | Union Station, 401 S. Jackson St. | Seattle, WA 981041-800-201-4900/ TTY Relay: 711 main@soundtransit.org | soundtransit.org

Languages:

中文 | Chinese
한국 | Korean
Русский | Russian
Español | Spanish
Tagalog
Tiếng việt | Vietnamese