Our contractors Balfour Beatty are making good progress on the A14 and M11 programme of essential works. The majority of works are being carried out as planned.
The recent heavy rain means we had to postpone works on the weekend of 30 and 31 January, on the M11 junction 13 northbound exit slip road.
Here's the current schedule of works that Balfour Beatty are carrying out on behalf of Highways England. Remember, schedules may change at short notice, for example due to bad weather.
Queries? Contact Highways England on 0300 123 5000 or info@highwaysengland.co.uk.
Know someone who'd like to receive these notifications? They can subscribe at www.highways.gov.uk/A14roadworks_subscribe.
When
|
Where
|
Activity
|
Diversion
|
18 Jan 2016
4 weeks
Overnight closures
|
A14 junction 33 westbound
|
Electro-kinetic works
|
Diversion route is off slip and directly back on |
5 weekend closures commencing 22 Jan (Fri 10pm –Mon 5am) |
M11 junction 13 northbound exit slip road
|
Complete reconstruction
|
Traffic from M11 northbound will be diverted to A14 westbound junction 30, A14 eastbound to junction 32, A14 westbound onto A428 to Cambourne junction, A428 eastbound onto A1303
|
25 Jan 2016 for 8 weeks
Overnight lane two closures in both directions
|
A14 junction 31 to junction 34
|
Central reservation barrier renewal
|
No diversion required. |
1 Feb 2016
6 nights complete closure
|
Junction 33 to 34 eastbound
|
Joint replacement
|
Diversion route is A10 to Ely, A142 to Newmarket, A14 westbound back to junction 34/33
|
9 Feb 2016
for 1 night
only
|
A14 junction 32 to junction 33 eastbound
|
Resurfacing
|
Eastbound motorway traffic will be diverted off at junction 32 and turned around to head west to Girton, exiting the A14 to the M11 south. Take the M11 south to junction 10, exiting the M11 and heading east on the A505, joining the A11 north to the A14 junction 36 where the diversion ends.
Eastbound local traffic will be diverted off at junction 32 and then south on the B1049 turning left on to Kings Hedges Road, heading east to the A1309 Milton Road. North on Milton Road to the A14 junction 33 for the A10 north.
|
|
|
|
|
Thank you for signing up to stay informed about the A14 and M11 Essential works. We'll do our utmost to complete these works quickly, avoid disturbance and keep noise to a minimum.
Once complete, the work will result in a smoother and safer A14, better bridges, and clearer directions to Addenbrookes Hospital.
|