Girder Installation Brings Bend Parkway Traffic Control Changes
Oregon Department of Transportation sent this bulletin at 03/14/2014 07:55 AM PDTMarch 14, 2014 For more information: Rex Holloway
ODOT Community Liaison
541-388-6178
Girder Installation Brings Bend Parkway Traffic Control Changes
BEND – Major construction at the US 97 (Parkway) Murphy Road project will bring traffic control changes there early next week.
ODOT and its contractor on the project, Hamilton Construction of Springfield, will be installing girders at the new Murphy Road Bridge on Tuesday night and Thursday night next week. To minimize disruption to traffic, the girders will be installed over the northbound lanes of the Parkway on Tuesday night and over the southbound lanes on Thursday night. However, lane changes will be necessary beginning Monday to accommodate this element of the project as follows:
Date |
Time |
Activity |
Traffic Control |
Mon., March 17 |
9 pm to 7 am |
Crane staging in center median |
Signal at Pinebrook/Parkway turned off. Intersection controlled by flaggers. Parkway traffic shifted to southbound lanes |
Tues., March 18 |
7 pm to 7 am |
Bridge girders placed over northbound lanes |
Signal at Pinebrook/Parkway turned off. Intersection controlled by flaggers; Parkway traffic shifted to southbound lanes |
Wed., March 19 |
9 pm to 7 am |
Reposition cranes |
Signal at Pinebrook/Parkway turned off. Intersection controlled by flaggers; Parkway traffic shifted to northbound lanes |
Th., March 20 |
7 pm to 7 am |
Bridge girders placed over southbound lanes |
Signal at Pinebrook/Parkway turned off. Intersection controlled by flaggers; Parkway traffic shifted to northbound lanes |
Fri., March 21 |
9 pm to 7 am |
Crane removal |
Signal at Pinebrook/Parkway turned off. Intersection controlled by flaggers; Parkway traffic shifted to northbound lanes |
Motorists should be aware of these traffic control changes and make alternate travel plans, if possible.
The US 97 Murphy Road project is a multi-year construction effort that will increase safety on the Bend Parkway and improve east-west connectivity in the City of Bend. It is a joint $27 million dollar project that is funded by the Jobs and Transportation Act, passed by the Oregon Legislature in 2009.
In addition to the Murphy Road Bridge, the project includes an overpass at the intersection of 3rd Street and the Parkway, will eliminate a stop light at that intersection, and eliminate a signal at US 97 (Parkway) and Pinebrook.
More information about this project is available at:
###