Welcome to the Design and Construction Connection a
quarterly newsletter that brings our subscribers up to date on projects that
the Public Works-Design and Construction Division has underway. In addition to our website, you can follow
our projects and team on Facebook and Twitter.
Brookside Drive
The recent fall weather allowed the
landscaping portion of the Brookside Drive Traffic Calming project to be
completed. The traffic calming project included installation of landscaped curb
bump-outs, landscaped medians, and some new sidewalk and wheelchair ramps at
intersections along the corridor. There were also two new catch basins
installed to improve storm drainage, one at Holden Street, and the other at
Glascock Street.
|
Kaplan Drive Traffic Calming
The Kaplan Drive project is on schedule and expected to be
complete by December 15, 2015. The sidewalk along Kaplan Drive from Lorimer to
Melbourne is complete. Bump outs have been added
along the corridor, the finishing touches are being
added to the median and bump out at the intersection of Melbourne Road, and the landscaping is underway along the
project corridor.
|
Leesville Road Project
The Leesville Road
Project is in the final stages, and is anticipated to be complete by the end of
the year. Concrete work along the corridor
is complete and contractors are currently
working on completing the final paving operations and the traffic signal
modifications.
|
The year 2016 looks to be a very busy year for
Design/Construction as we have several
projects scheduled to start construction this winter.
Sandy Forks Road widening
The construction contract for this project was awarded to Carolina Sunrock LLC at the
November 3, 2015, City Council Meeting.
The pre-construction meeting is planned
for later this month, and construction is
anticipated to begin early this winter. Utility
relocations by Duke-Progress are already
underway along the corridor in advance of the upcoming roadway construction.
The project will widen the corridor
to a three lane road with curbs, gutters and sidewalks and bike lanes on both
sides of the road from Six Forks Rd to Falls of Neuse Rd. This project is also
Raleigh’s first Greenroads Project. The
Greenroads Rating System is a sustainability rating system for roadway design
and construction projects. Greenroads was established in 2010 and is a very
similar process to the LEED certification program for building projects.
The project
will include three stormwater management devices, including water treatment in
one of the medians, as well as LED street lighting.
|
|
Lenoir & South Street Two-way
Conversion Project
The construction contract for the Lenoir
and South Street Project was awarded to Moffatt Pipe. Construction will begin in January and will be completed by
December 2016. The project will be converting both Lenoir Street and South
Street into two-way streets, adding bike lanes and sidewalks, to both sides of
the street where missing. The water and sewer infrastructure along these
corridors are also being replaced as part of this project.
|
Transylvania Avenue Street Petition Project
Carolina Sunrock was awarded the construction contract for the Transylvania Avenue
Project. Construction will begin in January and be completed in September 2016.
The project includes widening and the addition of curb and gutter from Hertford
Street to Beaufort Street.
|
Buck Jones Road Widening Project
The bidding phase of the Buck Jones Road
Project is scheduled to begin this December and construction is anticipated to
begin early this spring. The widening of Buck Jones Road will begin near Farmgate
Road and extend to Xebec Way and includes widening the roadway to a three lane
road with curb and gutter, sidewalks, and bike lanes on both sides of the
road. The project also includes two new
single lane roundabouts at Farmgate Road and Bashford Road and multiple
improvements to transit stop locations along the corridor.
|
1-40 Bridges Retrofit Project, Part A
The construction contract for the I-40
Bridges Retrofit Project was awarded to Fred Smith Company Construction.
Construction is scheduled to begin in January and completion is scheduled for December 2016. The
project will provide sidewalks along the I-40 overpasses at Buck Jones Road,
Avent Ferry Road, and Rock Quarry Road bridges.
|
Six Forks Road Sidewalk Project
Narron Contracting was
awarded the construction contract for the Six Forks Road Project. Construction is
scheduled to begin in January and be completed by July 2016. The project will be
installing sidewalk to the north side of Six Forks road from Coleridge Road to
Wake Forrest Road and includes a box culvert extension on the north side of the
roadway.
|
Capital
Boulevard Pedestrian Improvement Project
The design phase of this project is now
complete. The project is currently advertising for bids through December 10,
2015. Keep an eye out for more information on this project at the beginning of
the New Year.
|
Hillsborough Street, Phase II
The right of way and easement acquisition
phase is in progress. The project is scheduled to advertise for bids in early
2016 and construction is slated to begin
this spring. Keep an eye out on the Hillsborough Street Facebook page as well
as our Twitter account, @Raleigh PWDC for news and updates on this project. The
projects web page will also be updated with current activity.
|
Mitchell Mill Road Widening
The City's real estate team has almost
finished the right of way and easement acquisition phase of this project. The
project is scheduled to advertise for construction bids this winter with
construction to begin early this spring. Mitchell Mill Road will be widened
to a four lane median divided road with curb, gutter and sidewalk from
Louisburg Rd to Forestville Rd.
|
Fox
Road Improvements
The City held the first of two public meetings on September 29, 2015. The
public was able to see preliminary plans for the corridor and make comments. These comments are currently being addressed by the
design team, and the next set of preliminary plans will be available for
public comment at the next public meeting scheduled this winter. Fox
Road will be gaining the installation
of missing sections of curb and gutter and sidewalks on east and west sides
between Spring Forest Road and Sumner Blvd.
|
Yonkers
Road Improvement Project
City staff and consultants are currently working on the preliminary plans for
this project while surveys are being conducted. The project schedule has been added to the website and as the project
progresses more information will be added. The street improvements, including widening
the roadway to include curb and gutter, bike lanes and a sidewalk on the south
side of the street from Capital Boulevard to New Bern Avenue.
|
Pullen
Road Extension Project
The Pullen Road Extension project is a joint venture public/private agreement
with the City of Raleigh, NC State, and the Catholic Diocese. The project
includes extending Pullen Road from Western Blvd to Centennial Pkwy with bike
lanes, medians, sidewalk, multi-use path, landscaping, and street lights. The
developer’s consultant is approximately 25% complete with the design plans for
this project and the first public meeting is scheduled for January.
|
|
The
City of Raleigh is committed to making Raleigh a more walkable city, and that
is evident by the 40 sidewalk projects we currently have listed on our web site.
There
are two different types of sidewalk projects, City-initiated projects that
typically occur along heavily traveled roadways included in the Comprehensive
Pedestrian Plan, and neighborhood sidewalk projects handled through the
Petition Program.
City-initiated projects
Fixing
gaps along high volume streets is the focus of City-initiated projects; these
sidewalks are ranked in the Raleigh
pedestrian plan based on a variety of factors.
Sidewalk Petition Projects
The
Sidewalk Petition Program provides citizens an opportunity to initiate sidewalk
construction to complete portions of the sidewalk network that have not been
identified by the Pedestrian Program. The program requires signatures from a
majority of property owners along the street and in most cases there are no
costs for residential property owners. Primarily intended for streets in
residential neighborhoods, but sidewalks along non-residential streets are considered on a case by case basis.
|
|
The
City of Raleigh wishes to promote safe and efficient public streets. The City’s
Traffic Calming Program helps residents
to determine if traffic calming treatments are
needed on their streets.
Streets
wider than 31 feet are evaluated for the
Neighborhood Streetscape Program; streets narrower than 31 feet may qualify as
Minor Traffic Calming Projects. If it is
determined that your street meets the qualifications for the
Neighborhood Streetscape Program, then it is ranked on the list according to
need. Neighbors along the highest scoring streets are invited to an informational meeting and asked to submit a
petition to have a Neighborhood Streetscape Project developed. If 75% of the
residents support the project, then the project moves to the next phase.
Neighborhood
Streetscape Projects undergo a conceptual design phase where citizen input is
crucial to the development of the project. Once the
conceptual design is approved by City Council, these projects come to
the Design/Construction Division for final engineering designs.
Currently, we have three Neighborhood Streets
Scape projects in progress. Kaplan Drive is scheduled to be complete at the end
of December. Glascock Street is scheduled to start construction in January, and
Milburnie Road, which is in the design phase and scheduled to be complete by
the summer of 2017.
More Information about Neighborhood Traffic Management
|
The
Design/Construction Division consists of 38 employees spread over five programs
(Roadway, CADD Services, Survey Services, Contract Inspections, and
Assessments/Petitions). With each newsletter, we like to spotlight one or two members of the team.
Jimmy
Upchurch Assessment
Supervisor
Jimmy
started with the city in 1986, as a meter reader with the Utility Billing Department. In 1989, he transferred to the Finance
Department/Revenue Division where he worked as an Assessment Clerk. In that position, he was mainly responsible for what
they called, the “backend” of assessments, the billing,
and collection of assessment accounts for the City. From there Jimmy
transferred to the Finance Department/Parking Violations Division in 1997 as a
Collections Specialist, responsible for vehicle booting for delinquent parking
tickets. In 1998, he transferred to the
Inspections Department/Permit Office as a Permit Specialist. Then in 1999 Jimmy transferred again, this
time to Central Engineering as an Assessment Specialist working on what they
called the “Front end” of assessments. He now works with calculating property
owner assessments associated with street and sidewalk construction and water
and sewer construction projects, and issuing street and sidewalk improvement
petitions to citizens under the City’s Petition Programs. It was in 2010 that Jimmy was promoted his
current position as the Assessment Supervisor, overseeing both the Assessment
and Petition programs.
Jimmy
is a Raleigh native, graduating from Needham Broughton High School in the late
seventies. He married his high school sweetheart on Valentine’s Day in 1981 and
has been
happily married ever since. They have three children, and they just welcomed their first grandchild into the
world this September and he
“absolutely loves being a grandpa.”
Family
time is of the utmost importance to Jimmy
and spends he weekends surrounded by his family. As seen in the above picture
Jimmy is an ardent Carolina Panther fan
and is raising the grand-baby to be the same.
|
In
our last newsletter, we congratulated
Billy Clevenger on being the recipient of the American Public Works
Association-North Carolina Chapter, H.W. Kueffner Award. In this newsletter, we say farewell to Billy. After a
long and distinguished career with both the City of Raleigh and NCDOT Billy
will be retiring at the end of December. Billy, we at Design/Construction wish
you a very happy retirement!
|
Have a questions or feedback email us we want to hear from you. |
|
|
|