Light Rail Construction Details - Minneapolis - May 19 - 25, 2012

Minneapolis Construction Update May 19 - 25, 2012


For all construction questions or concerns, call the Construction Hotline:  (651) 602-1404


Schedules subject to change due to weather and other unforeseen circumstances! 
Check www.centralcorridor.org frequently for the latest updates or follow the twitter feed at www.twitter.com/cclrt. 

Photos of the Flyover Bridge over I-35W
Civil construction is scheduled to be complete at the end of the month for the area connecting downtown Minneapolis toward the West Bank.  Work for this segment included the construction of a new flyover bridge crossing I-35W, retaining walls, and track work to connect to the existing Hiawatha Light Rail Line.

Systems work will continue in the area through 2013 to add the power system for the light rail and communication system. For details on the schedule for the project  and upcoming completion milestones, view the West Bank 2012 Construction Overview online.