County Road 101 (Bushaway Road)

Generic Save the Date AB banner

County Road 101 (Bushaway Road) in Minnetonka, Wayzata and Woodland update

County Road 101 paved in time for Thanksgiving

The contractor plans to lay the first base layer of pavement as early as next week, weather permitting. Once reopened, traffic can travel Bushaway Road (County Road 101) between Minnetonka Boulevard and Eastman Lane/McGinty Road. Right now, we expect the roadway to be open for Thanksgiving weekend. We will send a notification out as soon as the road reopens.

In preparation for the pavement crews continue to finish installing storm sewer and grading gravel. They are also grading for the bike trail.

 

n cause

Construction update

While the weather continues to be on our side, crews are working on several activities throughout the project corridor:

  • Excavating in the railroad corridor in preparation for the shoofly, or temporary tracks
  • Installing stone on retaining walls
  • Connecting and relocating utilities
  • Temporary paving of driveway aprons
  • Installing permanent grass seed in many areas

Work zone safety

Thank you for slowing down and paying attention in work zones. Staying alert and dedicating your full attention to driving keeps you and our crews safe. 

For more information

Hotline: 866-981-1101 

Email: countyroad101@hennepin.us

Website: www.hennepin.us/countyroad101       

Twitter: @hennepinCR101


See active projects on our interactive road construction map.

Learn more about how transportation is connecting people to places.