December 2014 Development Services Construction Updates

Construction Updates

The Development Services Department strives to update those interested in private construction in the City of Palo Alto.  The purpose of this email notification is to give the reader construction related updates in the City of Palo Alto.  The following projects are currently in either plan review or under construction.  This update is sent monthly to provide a description of work, share a recent picture of the site or rendering, and provide a current status of the project. The majority of these projects replace or improve existing buildings.  Details about the previous structure are included at the bottom of each project description.  Please direct any questions to the Development Services Director Peter.Pirnejad@cityofpaloalto.org

Targeting Total Transparency,

1

Peter Pirnejad
Director, Development Services Department


636 Waverley

This project is a new 10,299 square foot, 4-story mixed-use building with 20 space parking garage. The commercial space will be located on the ground floor.  Residential units will be on the upper three floors. The permit has been issued and the project is approximately 3% complete.  This project replaces an existing building of approximately 1316 sf.

636 Waverley

4329 El Camino Real, The Hilton Homewood Hotel

4329 El Camino

This project is a new 111,585 square foot, 4-story hotel that contains 138 rooms located above a one level underground parking garage with 137 parking spaces. Currently a TCO is issued for limited use, and progress is in the final stages of construction. The project is approximately 95% complete. This project replaces an existing building of approximately 64,263 sf.


4214 El Camino Real, The Hilton Garden Inn

This project is a new 105,685 square foot, 4-story hotel that contains 174 rooms located above a two-level underground parking garage with 178 parking spaces. Currently site work, interior finishes and the kitchen installation are underway. The project is approximately 80% complete. This project replaces an existing building of approximately 6,296 sf.

4124 El Camino

300 Pasteur Drive, Stanford Parking Garage

300 Pasteur

This project is a new 5-level parking garage that includes an auditorium at the roof level.  Two of the five levels of parking are located below grade with 970 parking spaces. Currently a TCO is issued for construction parking, while work continues at the façade installation, site work, and multi-trade work at accessory areas. Completion of the parking garage will be in conjunction with the new hospital. The project is approximately 82% complete. This does not replace existing building sf.


780 Welch Road, Medical Office Building

This project is a new 31,353 square foot, 3-story medical office building located above one level of underground parking with 150 parking spaces. Currently a TCO has been issued and approved. The project is approximately 98% complete. This project replaces an existing building of approximately 24,678 sf.

780 Welch

2865 Park Boulevard, Park Plaza

Park Plaza

This project is a new 3-story mixed-use building located above one level of underground parking with 295 parking spaces. The ground level will contain 47,000 square feet of commercial office space. The second and third levels, totaling 101,500 square feet, contain 85 residential units. Currently, construction at the second level continues, and construction at the third level has begun. The project is approximately 27% complete.This project replaces an existing building of approximately 52,709 sf.


260 California Avenue

This project is a new 30,000 square foot, 3-story mixed-use commercial building located above one level underground parking garage with 42 parking spaces. Currently interior finishes are underway. A tenant has been selected, and TI work has begun. The project is approximately 95% complete. This project replaces an existing building of approximately 11,290 sf.

260 California

2650 Birch Street, Birch Plaza

2650 Birch

This project is a new 24,827 square foot, 3-story mixed-use structure located above a one level underground parking with 42 parking spaces. The ground level will contain 10,556 square feet of retail and business space. Eight 2-story rental apartment units will be located on second and third floors. Currently the third floor steel stud framing is complete, the exterior is sheathed, the roof pan deck construction continues, and plumbing rough-in continues. The project is approximately 57% complete. This does not replace existing building sf.


2080 Channing Avenue, Edgewood Plaza

This project is an approximately 20,000 square foot, three building relocation/rehabilitation of an Eichler-designed neighborhood mixed-use commercial shopping center. It also includes construction of 10 new 3,000 square foot single-family homes with attached garages. To complete the 3.6 acre development a .22-acre park will be completed near the end of the project. Currently temporary occupancy has been granted to large portion of the commercial shopping center and final construction activities are taking place. At the single-family residences, sheetrock is installed, while work on the interior finishes continues. Exterior stucco is now complete. The project is approximately 85% complete. This project replaces an existing building of approximately 37,900 sf.

2080 Channing

537 Hamilton Avenue

537 Hamilton

This project is a new 15,000 square foot, 2-story office building located above a one level underground parking garage with 19 parking spaces. Currently a TCO has been issued, and the core and shell are nearing completion. The project is approximately 98% completee.This project replaces an existing building of approximately 4588 sf.

This project replaces an existing building of approximately 4588 sf.


490 San Antonio Avenue, Gideon Hausner Jewish Day School

This project is a new 17,602 square foot single-story gymnasium and classroom building.  It also includes an 81,643 square foot commercial improvement including a new playing field, parking lot with 119 parking spaces and private road. Currently exterior finishes are nearly complete, and drywall installation is underway. Interior finishes are scheduled to start in the next few weeks. The project is 75% complete.This does not replace existing building sf.

490 San Antonio

135 Hamilton Avenue

135 Hamilton

This project is a new 27,915 square foot, 3-story mixed-use building located above a one level underground parking garage with 47 parking spaces. Retail space will be located on the ground level and office space will be located on the upper two floors. Currently construction at the second floor has begun, and the three levels of parking below street level are complete. The project is approximately 30% complete. This does not replace existing building sf

http://135hamiltonave.com/

 


1701 Page Mill Road, Theranos

This project is a new 115,600 square foot, 2-story commercial building located above a one level underground parking garage with 300 parking spaces. Currently the shell of the building has been granted a Final, and Phase One of the TI portion of the project has a TCO. The project is approximately 98% complete. This project replaces an existing building of approximately 67,000 sf.

1701 Page Mill

213 Quarry Road, Medical Office Building

213 Quarry

This project is a new 95,578 square foot, 4-story above basement medical office building. There is no vehicle parking in the building.  Both the shell and TI work are being constructed at the same time. Currently TI installations from the basement and through the roof levels are underway, as are preparations for the exterior curtain walls. The project is 40% complete. This project replaces an existing building of approximately 13,831 sf.


711 El Camino Real, The Clement

New 4-story hotel with a basement for underground parking and a pool on the roof.  6,897 square feet of commercial space, 13,027 square feet of hotel rooms, and 6,888 square feet of parking. There are 23 hotel rooms. Currently column and wall steel are being installed above the first floor podium deck. The project is approximately 15% complete.  This project replaces an existing building of approximately 1,490 sf.

711 ECR

611 Cowper St

611 Cowper

New 4-story mixed use building with two levels of underground parking. 62,818 square feet of commercial space, 6,712 square feet of residential, and 27,941 square feet of parking. Currently construction at the second level has begun. The project is 35% complete.

This project replaces an existing building of approximately 8,746 sf.

http://611-cowper.com/


1400 Page Mill Rd

This project is a 2-story commercial building with 89,000sf above a 45,500sf basement with 119 parking spaces, and 171 parking spaces outside the building. Currently all concrete decks are poured, rooftop curbs are being installed, and framing has begun. The project is 30% complete.This project replaces an existing building of approximately 86,925 sf.

1400 PageMIll

50 El Camino Real, Ronald McDonald House

50 ECR

New 3-story with build out and one level of underground parking. 51,637 square feet of commercial and short stay residential and 19,719 square feet of parking. Project includes 71 parking spaces. Currently foundation construction is nearing completion. The project is approximately 20% complete.   This does not replace existing building sf.


1845 El Camino Real

New 3-story mixed use building. 7,705 square feet of commercial/retail shell space. Currently structural steel above the third level is being installed. The project is approximately 20% complete.  This does not replace existing building sf.

1845 ECR

240 Hamilton Ave - Commercial/Residential Building

240 Hamilton

This project is a new 17,500 sf, 4-story mixed use building. First 3 floors designated for commercial and residential on the top floor. No construction started.


CIP PROJECTS


Magical Bridge Playground, Mitchell Park

This project is a restoration and upgrade of the bridge at Mitchell Park, new concrete walkways and repairs to existing asphalt walkways, new landscaping and irrigation.  Currently the plaza entrance seating concrete walls and foundation piers for the play structure are now installed. The project is approximately 70% complete.

Magical Bridge

City Hall, First Floor Mezzanine and Second Floor Remodel

City Hall

 This project is a remodel of City Hall on the first and second floors. Currently, all-trades work continues. The project is approximately 60% complete.

First floor: The two new conference rooms are complete except for the audio/visual components. The two new restrooms are complete except for some of the accessory components. Utilities customer service area is complete. Remaining work:

1)  Main core tower cladding and audio/visual components.

2)  Revenue collections counter upgrade.

3)  Renovation of old Council Conference Room.

Second Floor: Half of this floor on the Ramona side, Utilities Department, is complete and occupied. The other half on the Bryant side, IT Department, is under construction.

Mezzanine: Construction will begin in about 6 weeks.

 


PROJECTS IN PLAN CHECK


3159 El Camino Real, Mixed-Use Building

This project is a 69,506 square foot, 4-story mixed-use building including 48 residential apartments, 16,100 square feet of retail and office space, and 15,400 square feet of new restaurant and commercial recreation space. The 30,000 square foot expansion of the existing underground parking will include 183 additional parking spaces. Plans were submitted in November of 2013. Seven of eight departments have approved the project

1

405 Curtner Avenue

2500 El Camino

New four story mixed use building (80,748 sf) that consists of two buildings connected by a walkway. The project contains 70 residential units and has 145 parking spaces. Plans were submitted in June 2014 and the project has gone through five rounds of plan check. Five of the seven departments have approved the project.


2500 El Camino Real

A 3-story, six (6) unit townhouse building. All six units have the same square footage. Area per unit is 1237 sf of habitable space and 460 sf of garage. There will be 14 parking spaces at this site. Plans were submitted in December of 2013 and the project has gone through four rounds of plan check. Seven  of eight departments have approved the project.

1

1700 Embarcadero, Staybridge Suites

0

New 4-story hotel with one level of underground parking. The area of the hotel is 114,091 sf and the area of the garage is 35,837 sf. Scope of work includes 147 hotel rooms and 169 parking spaces. Plans were submitted in October 2013 and the project has gone through four rounds of plan check. Six of eight departments have approved the project


500 University Ave - Garage

This project consists of 56,430 square feet of foundation and below-grade parking for a future 3-story office and retail building with 4,938 square feet of occupied roof deck and 2 split level of below grade parking with 62 parking spaces. Four of seven departments have approved the project.

garage

1501 California: Mayfield California Ave

1501 Mayfield

This project consists of two condo buildings, a fitness building (1720 sf), a community building (2700 sf), and 68 new homes. Condo Building 1 contains 58 units (116,356 sf) and Condo Building 2 contains 54 new units (122,817 sf). Plans were submitted in June 2014 and the project has gone through one round of plan check. Four of eight departments have approved this project.


2180 El Camino Real College Terrace

The project includes a podium structure with 2 levels of underground parking, two 3-story commercial buildings connected by a walkway (52,504 sf), and a 2 story eight unit multifamily building (5304 sf). Plans were submitted in May 2014 and the project has gone through three rounds of plan check. Four of eight departments have approved the project.

terrace

2209-2215 El Camino Real

2009

A proposed 9571 square foot 3-story mix-used building, to include a ground floor financial service, second floor office space and third floor residential single unit; with 5 proposed parking stalls. Five of seven departments have approved the project.


103 El Camino Real – El Camino Real Park

This project is a new softball field, trash enclosure, and a 340 square foot score keeper structure as well as new synthetic soccer/lacrosse field, electrical service upgrade to 400amp, expanding the existing parking lot, and a new 913 square foot restroom. All departments have approved the project – waiting to be issued.

El Camino Park

180 EL CAMINO REAL

180 El Camino

Stanford Mall redevelopment and site improvements.  Includes 4 new shell buildings totaling approximately 134,000 sf which replaces the old Bloomingdales building.  Three of the eight departments have approved the project.