Development Services Construction Updates - April/2014

Construction Updates

4329 El Camino Real, The Hilton Homewood Hotel

1

This project is a new 111,585 square foot, 4-story hotel that contains 138 rooms located above a one level underground parking garage with 137 parking spaces.  The exterior stucco is currently being applied, and sheetrock is being installed at fourth floor level.  The project is approximately 65% complete.


4214 El Camino Real, The Hilton Garden Inn

This project is a new 105,685 square foot, 4-story hotel that contains 174 rooms located above a two-level underground parking garage with 178 parking spaces.  Currently fourth floor hotel rooms are being framed.  The project is approximately 30% complete.

2

300 Pasteur Drive, Stanford Parking Garage

3

This project is a new 5-level parking garage that includes an auditorium at the roof level.  Two of the five levels of parking are located below grade with 970 parking spaces.  Currently the second level slab and columns are nearing completion, and the lower level lighting and interior room structures are being constructed.  The project is approximately 55% complete.


780 Welch Road, Medical Office Building

This project is a new 31,353 square foot, 3-story medical office building located above one level of underground parking with 150 parking spaces.  Currently interior framing is being installed on all levels.  The project is approximately 50% complete.

4

3431 Hillview Avenue, VMWare Campus

1

This project consists of four phases. Third phase is nearing completion and the fourth phase will be something to look forward to.

Building CSD: This project is a 15,036 square foot cafeteria.  Final construction activities are taking place.  The project is approximately 95% complete.

Parking Garage 1: This project is a 3-level parking garage with 680 parking spaces.  Currently temporary occupancy has been granted and final construction activities are taking place.  The project is approximately 95% complete.

Parking Garage 3: This project is a 4-level parking garage with 750 parking spaces.  Currently temporary occupancy has been granted final construction activities are taking place.  The project is approximately 95% complete.

Site Improvements: Landscaping, stairways, walkways and railings are currently being completed.  The project is approximately 85% complete.


2865 Park Boulevard, Park Plaza

This project is a new 3-story mixed-use building located above one level of underground parking with 295 parking spaces. The ground level will contain 47,000 square feet of commercial office space.  The second and third levels, totaling 101,500 square feet, contain 85 residential units.  Currently, foundation and underground utilities infrastructures are underway on the underground parking garage.  The project is approximately 8% complete.

3

1213 Newell Road, Main/Riconada Library

6

This project is an extensive remodel, addition and upgrade of the existing Main/Rinconada library.  The addition is 4,100 square feet, and the remodel covers 25,000 square feet. Currently framing activities are underway.  The project is approximately 30% complete.


260 California Avenue

This project is a new 30,000 square foot, 3-story mixed-use commercial building located above one level underground parking garage with 42 parking spaces.  Currently the second floor deck is being prepared to receive concrete.  The project is approximately 20% complete.

1

2650 Birch Street, Birch Plaza

2

This project is a new 24,827 square foot, 3-story mixed-use structure located above a one level underground parking with 42 parking spaces.  The ground level will contain 10,556 square feet of retail and business space.  Eight 2-story rental apartment units will be located on second and third floors.  Currently structural steel erection is underway.  The project is approximately 20% complete.


3700 Middlefield Rd, Mitchell Park Library & Community Center

The Library is a 2-story structure consisting of 21,466 square feet. The Community Centers are two additional 1-story structures with a total square footage of 16,180 square feet.  Currently final construction activities are taking place.  The project is approximately 94% complete.

3

4041 El Camino Way, The Avant

4

This project is a new 71,000 square foot, 3-story mixed-use building that contains 44 elder care dwelling units and is located above an underground parking garage with 41 parking spaces. Currently temporary occupancy has been granted and final construction activities are taking place.  The project is approximately 95% complete.


101 Lytton Avenue, Lytton Gateway

This project is a new 138,951 square foot, 3-story mixed-use building that includes a 50,000 square foot office and retail space. Additionally, there are 1,600 square feet of subsidized rental property for a Palo Alto-based nonprofit organization on the ground level. This new office building is located over two and half levels of underground parking with 134 parking spaces.  Survey Monkey will be occupying the second and third floors of this new building.  Currently temporary occupancy has been granted for major tenant Survey Monkey and final construction activities are taking place.  The project is approximately 90% complete.

5

2080 Channing Avenue, Edgewood Plaza

7

This project is an approximately 20,000 square foot, three building relocation/rehabilitation of an Eichler-designed neighborhood mixed-use commercial shopping center.  It also includes construction of 10 new 3,000 square foot single-family homes with attached garages.  To complete the 3.6 acre development a .22-acre park will be completed near the end of the project.  Currently temporary occupancy has been granted to large portion of the commercial shopping center and final construction activities are taking place.  Framing has started on five of the ten new homes and all ten foundations have been installed. The project is approximately 52% complete.


537 Hamilton Avenue

This project is a new 15,000 square foot, 2-story office building located above a one level underground parking garage with 19 parking spaces.  Currently a mixture of framing and drywall activities are taking place on both levels.  The project is approximately 50% complete.

8

490 San Antonio Avenue, Gideon Hausner Jewish Day School

8

This project is a new 17,602 square foot single-story gymnasium and classroom building.  It also includes an 81,643 square foot commercial improvement including a new playing field, parking lot with 119 parking spaces and private road.  Currently underground infrastructure is underway.  The project is approximately 5% complete.


135 Hamilton Avenue

This project is a new 27,915 square foot, 3-story mixed-use building located above a one level underground parking garage with 47 parking spaces.  Retail space will be located on the ground level and office space will be located on the upper two floors.  Currently underground infrastructure and shoring activities are underway.  The project is approximately 5% complete.

0

1701 Page Mill Road, Theranos

1

This project is a new 115,600 square foot, 2-story commercial building located above a one level underground parking garage with 300 parking spaces.  Currently the shell of the building is nearing completion and tenant improvement portion of the project is just starting.  The project is approximately 70% complete.


180 El Camino Real, Bloomingdales - Stanford Shopping Center

This project is a new 107,000 square foot, 3-story retail building.  Currently the structural steel decks are being prepared to receive concrete placement.  The project is approximately 20% complete.

0

998 San Antonio Avenue, The Mosque

9

This project is a new 11,436 square foot, 2-story mosque structure with two attached residential units. Currently final construction activities are taking place.  The current project is approximately 97% complete.


180 Hamilton Avenue, Hotel Epiphany

This project is a modification/remodel of the existing 50,888 square foot, 8-story former Casa Olga building. A new restaurant and lobby is located on the ground floor, 86 hotel rooms are located on the remaining seven floors.  Currently temporary occupancy has been granted and final construction activities are taking place.  The project is approximately 99% complete.

0

PROJECTS IN PLAN CHECK


3159 El Camino Real, Mixed-Use Building

1

This project is a 69,506 square foot, 4-story mixed-use building including 48 residential apartments, 16,100 square feet of retail and office space, and 15,400 square feet of new restaurant and commercial recreation space. The 30,000 square foot expansion of the existing underground parking will include 183 additional parking spaces. Plans were submited in November of 2013. Five of eight departments have approved the project.


711 El Camino Real, The Clement

New 4-story hotel with a basement for underground parking and a pool on the roof.  Area of commercial space 6897 sf, area of hotel rooms 13,027 sf, and area of parking is 6888 sf. There are 23 hotel rooms. Plans were submitted in December 2013 and the project has gone through one round of plan check.

1

405 Curtner Avenue

1

A 3-story, six (6) unit townhouse building. All six units have the same square footage. Area  per unit is 1237 sf of habitable space and 460 sf of garage. There will be 14 parking spaces at this site. Plans were submitted in December of 2013 and the project has gone through one round of plan check. Three of seven departments have approved the project.


50 El Camino Real, Ronald McDonald House

New 3-story with build out and one level of underground parking. Area of commercial and short stay residential: 51,637 sf and area of parking: 19,791 sf. Project includes 71 parking spaces. Plans were submitted in December of 2013 and the project has gone through one round of plan check. Two of eight departments have approved the project.

2

611 Cowper

4

New 4-story mixed use building with two levels of underground parking. Area of commercial space is 62,818 sf, area of residential is 6,712 sf, and area of parking is 27,941 sf. Plans were submitted in November of 2013 and the project has gone through two rounds of plan check. Five of eight departments have approved the project.


1845 El Camino Real

Cold shell for a new 3-story mixed use building. The area of the building is 7705 sf. The project was submitted in November 2013 and the project has gone through three rounds of plan check.  Six of eight departments have approved the project.

2

1700 Embarcadero, Staybridge Suites

0

New 4-story hotel with one level of underground parking. The area of the hotel is 114,091 sf and the area of the garage is 35,837 sf. Scope of work includes 147 hotel rooms and 169 parking spaces. Plans were submitted in October 2013 and the project has gone through four rounds of plan check. Six of eight departments have approved the project.


636 Waverley St

2

This project is a new 10,299 square foot, 4-story mixed-use building with 20 space parking garage. The commercial space will be located on the ground floor.  Residential units will be on the upper three floors. The project was submitted in October 21, 2014 and the project has gone through two rounds of plan check.  Four of seven departments have approved the project.